AGL38.75▲ 0.68 (0.02%)AIRLINK138.15▲ 1.3 (0.01%)BOP5.43▲ 0.02 (0.00%)CNERGY3.83▲ 0.07 (0.02%)DCL7.92▲ 0.08 (0.01%)DFML46.3▲ 0.4 (0.01%)DGKC81.6▲ 1.24 (0.02%)FCCL29.74▲ 0.83 (0.03%)FFBL56.6▼ -0.44 (-0.01%)FFL9.48▲ 0.12 (0.01%)HUBC105.62▲ 1.91 (0.02%)HUMNL14.36▲ 0.35 (0.02%)KEL4.26▲ 0.53 (0.14%)KOSM8.44▲ 0.26 (0.03%)MLCF38.23▲ 0.75 (0.02%)NBP69.32▲ 1.03 (0.02%)OGDC168.05▲ 1.18 (0.01%)PAEL25.4▲ 0.27 (0.01%)PIBTL6.9▼ -0.15 (-0.02%)PPL131.2▲ 1.7 (0.01%)PRL23.92▲ 0.3 (0.01%)PTC15.96▲ 0.16 (0.01%)SEARL60.45▼ -0.52 (-0.01%)TELE7.04▲ 0.05 (0.01%)TOMCL36.39▲ 0.48 (0.01%)TPLP7.89▲ 0 (0.00%)TREET15.5▲ 0.59 (0.04%)TRG45.06▲ 0.19 (0.00%)UNITY25.75▲ 0.33 (0.01%)WTL1.23▲ 0 (0.00%)

Stage-1 of Concrete-Starter Dam at Dasu HPP completed

Share
Tweet
WhatsApp
Share on Linkedin
[tta_listen_btn]

In a significant development towards the implementation of the Dasu Hydropower Project (DHPP), WAPDA announced on Wednesday evening that Stage-1 of the Concrete-Starter Dam has been completed upstream of the main dam site.

Stage-1 of the concrete Starter Dam was finished earlier this month, just before the high flow season in River Indus. WAPDA’s statement described it as a major achievement for the project team, Gwadar Pro reported on Thursday.

According to the project design, the Starter Dam for DHPP is divided into two stages. Stage-1 has been completed up to an elevation of 785 meters, while Stage-2 is planned up to an elevation of 798 meters above sea level.

Following the high flow season in October this year, the construction of Stage-2 of the Starter Dam will commence and is expected to be completed during the upcoming low-flow season.