AGL40.16▲ 0.13 (0.00%)AIRLINK131.73▲ 2.42 (0.02%)BOP6.69▼ -0.11 (-0.02%)CNERGY4.47▼ -0.17 (-0.04%)DCL8.82▲ 0.19 (0.02%)DFML40.61▼ -0.34 (-0.01%)DGKC84.08▼ -1.66 (-0.02%)FCCL32.34▼ -0.66 (-0.02%)FFBL68.61▲ 2.08 (0.03%)FFL11.35▼ -0.11 (-0.01%)HUBC111.76▲ 1.18 (0.01%)HUMNL14.31▼ -0.32 (-0.02%)KEL5.22▼ -0.02 (0.00%)KOSM8.98▲ 0.87 (0.11%)MLCF39.43▼ -0.64 (-0.02%)NBP60.29▼ -0.22 (0.00%)OGDC194.94▼ -0.53 (0.00%)PAEL26.69▼ -0.41 (-0.02%)PIBTL7.48▼ -0.16 (-0.02%)PPL155.77▼ -0.05 (0.00%)PRL26.68▼ -0.69 (-0.03%)PTC18.3▼ -0.26 (-0.01%)SEARL83.02▼ -2.08 (-0.02%)TELE8.23▲ 0.33 (0.04%)TOMCL34.55▼ -0.33 (-0.01%)TPLP8.81▼ -0.41 (-0.04%)TREET16.7▼ -0.11 (-0.01%)TRG62.45▼ -0.41 (-0.01%)UNITY27.44▼ -0.31 (-0.01%)WTL1.28▼ -0.02 (-0.02%)

PR approves PC-I for rehabilitation of 33-km track in Balochistan

Share
Tweet
WhatsApp
Share on Linkedin
[tta_listen_btn]
Staff Reporter
Islamabad

Pakistan Railways has approved the PC-I for rehabilitation of a 33.50-kilometer track ‘through sleeper renewal’ between Quetta-Bostan and Quetta-Chaman section.

“The track will not only facilitate the passengers, but also connect three major cities of the province,” an official in the Ministry of Railways said.

He said railway network in Balochistan province mainly consisted of Quetta Division having Dera Allah Yar Sibi-Quetta, Quetta-Chaman, Sibi-Khost, Spezend-Dalbandin-Taftan, Bostan-Zhob which were closed for the last 15 years.

The official said there were two passenger trains namely Jaffer Express (40Up, 39 Down) and Chaman Passenger (349Up, 350 Down) operating in Balochistan while no stations had been closed during the last 15 years in Quetta division.

He said the overall length of the railway track in Balochistan was 1470.36 kilometer including the closed Bostan-Zhob section.

“The most of the track is more than 100 years old and on certain stretches, engineering speed restrictions have been imposed due to deferred maintenance and owing to resource constraints,” he said adding that the routine maintenance of track was being carried out with available resources.

To improve railway services in Balochistan, he said, the present government was taking several steps like approval of PC-I for the track’s rehabilitation and the rehabilitation of another 100-km track between Ahmedwal Dalbadin on Quetta-Taftan section.

The official said that 100-km rehabilitation of track between Nokundi Kohi-Taftan on Quetta-Taftan section while 160.024 kilometers rehabilitation of track between Bostan-Chaman on Quetta-Chaman section would be carried out.

Related Posts

Get Alerts