AGL40.1▼ -0.11 (0.00%)AIRLINK127.25▼ -0.39 (0.00%)BOP6.69▲ 0.02 (0.00%)CNERGY4.47▲ 0.02 (0.00%)DCL8.65▼ -0.08 (-0.01%)DFML40.65▼ -0.51 (-0.01%)DGKC85.6▼ -0.51 (-0.01%)FCCL32.78▲ 0.22 (0.01%)FFBL64.2▼ -0.18 (0.00%)FFL11.67▲ 0.06 (0.01%)HUBC111.99▼ -0.47 (0.00%)HUMNL14.97▲ 0.16 (0.01%)KEL5.15▲ 0.11 (0.02%)KOSM7.39▲ 0.03 (0.00%)MLCF40.4▲ 0.07 (0.00%)NBP61.25▲ 0.17 (0.00%)OGDC192.3▼ -1.88 (-0.01%)PAEL26.88▼ -0.03 (0.00%)PIBTL7.25▼ -0.03 (0.00%)PPL153.4▲ 0.72 (0.00%)PRL26.35▲ 0.13 (0.00%)PTC16.77▲ 0.63 (0.04%)SEARL85.99▲ 0.29 (0.00%)TELE7.65▼ -0.02 (0.00%)TOMCL33.75▼ -2.72 (-0.07%)TPLP8.81▲ 0.02 (0.00%)TREET16.64▼ -0.2 (-0.01%)TRG63.6▲ 0.86 (0.01%)UNITY28▼ -0.2 (-0.01%)WTL1.31▼ -0.03 (-0.02%)

Construction of 900MW RLNG based power project to commence next month

Share
Tweet
WhatsApp
Share on Linkedin
[tta_listen_btn]

Staff Reporter

Karachi

The construction of K-Electric’s $650 million 900MW RLNG-based Bin Qasim Power Station (BQPS)-III will commence in December. The project has received all required approvals and is part of KE’s planned initiatives resulting in investments of around US$3 billion across the power value chain over the next few years.
The project was conceived in 2016 and after the completion of feasibility studies it was approved and publicly announced in 2017. Although the project timeline has been affected due to delay in finalization of KE’s multi-year tariff, the power utility is determined to execute it on a fast track, and according to the project contracts signed last month, the plant is expected to start producing electricity by summer of 2021.
According to Moonis Alvi, CEO, KE, “The project is a major private sector investment in the country’s power sector and is in line with K-Electric’s vision of diversifying its fuel mix besides enhancing generation fleet efficiency. We have also re-negotiated the terms of the contract and the first unit of 450MW will be commissioned in only 19 months instead of 24 months, thus greatly reducing the time in which Karachi will start reaping the benefits.
The 900MW RLNG project will be a highly efficient combined cycle plant with an efficiency of around 60%. In addition to bridging the demand for electricity, this plant will also enable us to gradually phase out some units of the aging and less efficient BQPS I plant which have been in service for more than 25 years.
After completion, BQPS-III will result in lower import costs for the government, affordable power for consumers and a much smaller carbon footprint as compared to furnace oil power plants.”
KE continues to move ahead in enhancing generation capacity, both through its own sources as well as independent power producers (IPP) and remains committed to continue investments across the value chain, which will further improve operational performance, thus benefiting consumers. KE is also actively pursuing the 700 MW coal-fired plant being built in collaboration with China Machinery Engineering Corporation (CMEC).
KE has also been actively engaged with the relevant stakeholders for additional off-take from the national grid; however, after a detailed study it was intimated to both KE and the Ministry of Energy that national grid could not provide the requested MWs from the existing interconnection infrastructure, on account of overloading and system stability concerns. Additionally, KE is already in negotiations with relevant stakeholders for import of 500MW from the under-construction nuclear power plants KANUPP II & III and if this additional 500MW is made available to KE, the power utility stands ready to invest in interconnections to evacuate that power to replace the remaining inefficient power plants.
However, construction of interconnection facilities will take at least two and a half years following the receipt of required approvals which will also take their due time.
So given the robust due diligence, current technical limitations to off-take additional power from the national grid, demand supply gap, transmission situation, efficiency and all related factors – the upcoming 900MW RLNG power plant is very crucial for Karachi and KE is committed to commission the project as soon as possible.

Related Posts