Pakistan Railways is spending Rs.1862.84 million for the rehabilitation of 518 kilometres of track between Kotri-Khanpur under the project of Immediate Track Safety Works (ITSW-I).
Despite financial constraints, the management of Pakistan Railways is putting maximum efforts into improvement in infrastructure including tracks, bridges, stations etc, an official in the Ministry of Railways told APP.
Under the project of rehabilitation of Karachi Port tracks, 24-kilometre tracks, 17 level crossings and seven bridges have been rehabilitated along with the replacement of turnouts.
The official said that Railway Dry Ports at Lahore (Mughalpura), Badami Bagh and Azakhel have been upgraded.
He said under the Immediate Track Safety Works (ITS W-II & IMTS W-III), the railway track between Tando Adam-Khanpur covering 456 kilometres would be rehabilitated at a cost of Rs. 4830.437 million and Rs.4875.461 million respectively by replacing the US components of the track by ensuring the safety of train operation.—APP