Staff Reporter Lahore
The flagship project under CPEC ±660 kV HVDC Matiari – Lahore Transmission Line has achieved its commercial operation date successfully on Wednes-day as per agreed timeline between National Trans-mission and Despatch Company Ltd (NTDC) and Pak Matiari-Lahore Transmission Line Company (PMLTC).
Prior to its COD, as many as 8 power tests on dif-ferent voltage levels were performed successfully.
The power test include Commissioning Tests (DC Station Tests) Lahore Commissioning Tests (DC Station Tests) Matiari, Mono-pole Low Power Sys-tem Tests (Upto 400 MW each pole), Bi-pole Low Power System Tests (Upto 800 MW Bi-pole), Mono-pole High Power Tests (2200 MW, each pole) (A5:),Bi-pole High Power Tests at Maximum Available Power .