Lahore Electric Supply Company is a Pakistani government-owned electric distribution company, which is responsible for supplying electricity to the districts of Lahore, Okara, Sheikhupura, Nankana and Kasur in the Punjab province.
It is required to apply for a new connection if you want to avail the electricity services offered by the LESCO in the above mentioned districts.
There is an online process to submit the application for the new meter connection.
Steps to Apply for the Lesco New Connection
Step 1: You can visit the given link (http://www.enc.com.pk/) to start the application process.
Step 2: During form submission you are required to submit the below information:
Choose one of your connection type from: Domestic, Commercial, Industrial, Agriculture, Tubewell, Temporary, General Services, Residential Colonies, Street Light
Enter National Tax Number (NTN)
Enter Sales Tax Registration Number (STRN)
Select your district related company like, for Lahore you have to choose LESCO
Choose your related sub-division
Application Status: Owner or Rental
Applicant name
Father name
NIC/CNIC number
Present address
Mobile number 1 & 2
Contact person name
Contact person mobile number
Contact person present address
Relationship with applicant
Email (optional)
No. of meter already installed
Minimum load (In KWh)
Premises address
Neighbor bill referenced number
Neighbor name and address
Choose meter installation company from: Shahid & Co or Sajjad Brothers
Step 3: You will also require to submit property details where you want to install the new electricity connection.
Step 4: After filling and uploading all required information and docs submit the application form
Step 5: Need to printout of your submitted application form
Step 6: Attach all above mentioned documents with this application
Step 7: Send or submit this complete file (including application form and required documents) to your related office
Step 8: LESCO demand notice will be issued after verification of the submitted documents and info
Step 9: Now next step is to pay the LESCO demand notice to mentioned bank
Step 10: After paying demand notice, copy should be submitted to the concerned office for further process
Step 11: In this final stage the concerned office will verify the demand notice payment and after verification they will installed the connection
What is the cost of single phase meter connection in Lesco?
The official website of Lesco says estimated new connection fee is Rs-7240 it recommends to contact the concerned office for confirm fee.
In various sub-division of Lahore, the Lesco offices are charging Rs18,000 to Rs25,000 for new single phase meter connection. The rate may vary in other districts where Lesco offers services.