AGL40▲ 0 (0.00%)AIRLINK129.06▼ -0.47 (0.00%)BOP6.75▲ 0.07 (0.01%)CNERGY4.49▼ -0.14 (-0.03%)DCL8.55▼ -0.39 (-0.04%)DFML40.82▼ -0.87 (-0.02%)DGKC80.96▼ -2.81 (-0.03%)FCCL32.77▲ 0 (0.00%)FFBL74.43▼ -1.04 (-0.01%)FFL11.74▲ 0.27 (0.02%)HUBC109.58▼ -0.97 (-0.01%)HUMNL13.75▼ -0.81 (-0.06%)KEL5.31▼ -0.08 (-0.01%)KOSM7.72▼ -0.68 (-0.08%)MLCF38.6▼ -1.19 (-0.03%)NBP63.51▲ 3.22 (0.05%)OGDC194.69▼ -4.97 (-0.02%)PAEL25.71▼ -0.94 (-0.04%)PIBTL7.39▼ -0.27 (-0.04%)PPL155.45▼ -2.47 (-0.02%)PRL25.79▼ -0.94 (-0.04%)PTC17.5▼ -0.96 (-0.05%)SEARL78.65▼ -3.79 (-0.05%)TELE7.86▼ -0.45 (-0.05%)TOMCL33.73▼ -0.78 (-0.02%)TPLP8.4▼ -0.66 (-0.07%)TREET16.27▼ -1.2 (-0.07%)TRG58.22▼ -3.1 (-0.05%)UNITY27.49▲ 0.06 (0.00%)WTL1.39▲ 0.01 (0.01%)

Govt opens up LNG sector

Share
Tweet
WhatsApp
Share on Linkedin
[tta_listen_btn]

Islamabad

Following the introduction of ease-of-doing-business strategy by the government, as many as five private sector companies were planning to set up Liquefied Natural Gas (LNG) terminals, having capacity to re-gasify 500-700 Million Cubic Feet per day (MMCFD) gas each.
“We do believe the LNG is here to stay, but we have decided that this sector has to be completely opened up. So, the government has allowed all five companies that wanted to set up their own terminals in Pakistan,” a senior official privy to petroleum sector developments told APP.
He said it was not the government job to decide who had the muscle, market clout and power to succeed. “It is for the market to decide.”
The official said the government’s footprint in the coming years in the energy as well as other sectors was going to shrink. “It is not only the government’s stated policy but fervent desire and intention.”
He said the government was going to do major restructuring on the pipelines side by converting them into ‘open access pipes’ and during the next two years, “We intend to separate transmission from distribution and open up the sector for use through private supplies and open access. Let the private sector compete with the government distribution companies and let them run faster and become more efficient.”
He said private sector companies including Exxon, Shell and Mitsubishi besides Spanish and French firms were poised to establish LNG terminals in Pakistan, who were considered the world leading players in energy sector.
The official said the federal cabinet had recently cleared the private sector companies, adding “A terminal, as per international standard, takes almost two years to complete once its construction starts.”
Currently, the official said, two LNG terminals were operating at Port Qasim Karachi and injecting around 1200 MMCFD gas in the distribution network, adding the capacity of Floating Storage and Re-gasification Units (FSRUs) was also being increased.
He said the Petroleum Division had planned to bring additional 400 MMCFD LNG in the system by December, out of which “200 MMCFD is guaranteed as tender had already been floated to ensure transparency.”—APP