AGL40.05▲ 0.05 (0.00%)AIRLINK130.5▲ 0.97 (0.01%)BOP6.75▲ 0.07 (0.01%)CNERGY4.48▼ -0.15 (-0.03%)DCL8.79▼ -0.15 (-0.02%)DFML40.9▼ -0.79 (-0.02%)DGKC81▼ -2.77 (-0.03%)FCCL32.9▲ 0.13 (0.00%)FFBL75.95▲ 0.48 (0.01%)FFL11.73▲ 0.26 (0.02%)HUBC109.6▼ -0.95 (-0.01%)HUMNL14.09▼ -0.47 (-0.03%)KEL5.4▲ 0.01 (0.00%)KOSM8.05▼ -0.35 (-0.04%)MLCF38.95▼ -0.84 (-0.02%)NBP63.5▲ 3.21 (0.05%)OGDC196.6▼ -3.06 (-0.02%)PAEL25.86▼ -0.79 (-0.03%)PIBTL7.47▼ -0.19 (-0.02%)PPL156.8▼ -1.12 (-0.01%)PRL26.1▼ -0.63 (-0.02%)PTC17.65▼ -0.81 (-0.04%)SEARL79.5▼ -2.94 (-0.04%)TELE7.9▼ -0.41 (-0.05%)TOMCL33.8▼ -0.71 (-0.02%)TPLP8.6▼ -0.46 (-0.05%)TREET16.62▼ -0.85 (-0.05%)TRG58.1▼ -3.22 (-0.05%)UNITY27.7▲ 0.27 (0.01%)WTL1.42▲ 0.04 (0.03%)

WAPDA Chairman visits under-construction 1530 MW-Tarbela 5th Extension

Share
Tweet
WhatsApp
Share on Linkedin
[tta_listen_btn]

 

WAPDA Chairman Engr. Lt. Gen (Retd) Sajjad Ghani Tuesday visited under-construction 1530 MW-Tarbela 5th Extension and reviewed the progress on the project.

The Chairman had a detailed visit of the key sites, which include the Raised Intake, the Tunnel and the Power house, and witnessed construction work going on there. During the on-site briefing, the Project Director and the Construction Manager briefed the Chairman about the milestone achieved on these sites.

Temporary support work in the tunnel is complete paving the way for commencement of construction on the connecting tunnel. Installation of equipment such as draft tubes of all three units – Unit No. 18, 19 and 20 – is in progress at the Power house Site.

While, the Contractor is all set to resume construction work on the Raised Intake structure once the water in the reservoir recedes to the required level.

Following the site visit, the Chairman presided over a meeting at the project office attended by the GM Tarbela Dam, PD T5, the Consultants and the Contractors.

Overall progress on the project was discussed during the meeting. It was briefed that construction is continuing on all 6 work fronts simultaneously. The project is likely to be completed in 2025-26.