AGL40.21▲ 0.18 (0.00%)AIRLINK127.64▼ -0.06 (0.00%)BOP6.67▲ 0.06 (0.01%)CNERGY4.45▼ -0.15 (-0.03%)DCL8.73▼ -0.06 (-0.01%)DFML41.16▼ -0.42 (-0.01%)DGKC86.11▲ 0.32 (0.00%)FCCL32.56▲ 0.07 (0.00%)FFBL64.38▲ 0.35 (0.01%)FFL11.61▲ 1.06 (0.10%)HUBC112.46▲ 1.69 (0.02%)HUMNL14.81▼ -0.26 (-0.02%)KEL5.04▲ 0.16 (0.03%)KOSM7.36▼ -0.09 (-0.01%)MLCF40.33▼ -0.19 (0.00%)NBP61.08▲ 0.03 (0.00%)OGDC194.18▼ -0.69 (0.00%)PAEL26.91▼ -0.6 (-0.02%)PIBTL7.28▼ -0.53 (-0.07%)PPL152.68▲ 0.15 (0.00%)PRL26.22▼ -0.36 (-0.01%)PTC16.14▼ -0.12 (-0.01%)SEARL85.7▲ 1.56 (0.02%)TELE7.67▼ -0.29 (-0.04%)TOMCL36.47▼ -0.13 (0.00%)TPLP8.79▲ 0.13 (0.02%)TREET16.84▼ -0.82 (-0.05%)TRG62.74▲ 4.12 (0.07%)UNITY28.2▲ 1.34 (0.05%)WTL1.34▼ -0.04 (-0.03%)

K-Electric committed to smooth power supply to city: CFO

Share
Tweet
WhatsApp
Share on Linkedin
[tta_listen_btn]

K-Electric remains committed in bringing Karachi to a power surplus position by 2022 through a series of planned investments across the power value chain.

These investments, which would be subject to regulatory approvals will allow KE to benefit consumers and the economy at large.

This was stated by Aamir Ghaziani, Chief Financial Officer of K-Electric at the Corporate Briefing, held via webinar, which was attended by analysts from leading brokerage houses and other stake holders

.The impact of COVID coupled with increased finance cost due to accumulated receivables from Government and its entities led to KE reporting a loss in FY 2020.

However, analysts were informed that first half of FY 2021 has shown improvement in key operational and financial indicators including 4.8% growth in sent-out, improvement in T&D losses by 0.6pp and reduction in interest rates. This has helped turn around KE back into profits in FY 21.

KE remains committed to its vision of taking Karachi to a power surplus position by 2022.

The upcoming 900 MW RLNG-based BQPS-III is proceeding as per expected timelines and the first unit of 450 MW is scheduled to come online by May 2021.

This power plant will also help improve KE’s generation fleet efficiency from 38% in FY 2020 to 48% in FY 2023.

Apart from this 350 MW of renewable energy projects are also in the pipeline.

Work on the 220 kV Dhabeji Grid and transmission lines has started and finalization of contractual arrangements for the off-take of additional 1,400 MW from National Grid (including 450 MW from existing interconnections) is in advanced stages.

KE is hopeful that the NTDC will complete necessary rehabilitation of the 220 KV Dhabeji grid along with implementation of “Cross Trip” scheme by March of 2021.

Conclusion of the interconnection agreement (ICA) with NTDC and power purchase agreement (PPA) with CPPA-G for 2,050 MW (existing 650 MW existing plus additional 1,400 MW) is crucial for off-take of additional power.

Project Sarbulandi, part of KE’s PKR 24 billion loss reduction investment from FY 17 to FY 23 is the power utility’s flagship initiative to uplift underdeveloped areas of Karachi by focusing not just on network health but also on community uplift activities and infrastructure development such as the construction of water filtration plants, rehabilitation of parks and schools and through free medical camps across the city.

As part of Sarbulandi the Company has continued with the conversion to Aerial Bundled Cable (ABC) with more than 800 Pole Mounted Transformers (PMT) converted to ABC during first half of FY 2021, and around 10,000 PMTs overall.

The impact is already being felt in parts of Korangi, Orangi and Landhi with up to four hours of load-shed reduction on average.

KE plans to convert all High Loss (HL) PMTs to ABC by 2023.

This will allow for continuity in loss-reduction and exempt more than 93% of service areas from load-shed.