City Reporter
A meeting was held at the Capital Development Authority office in Islamabad to review the work of installing fencing on the expressway.
It was clarified in the meeting that the fencing work on both sides would be completed by the end of June 2021.
The plan is to build a fence from Faizabad to Coral. The project will be completed by June 30. All cemeteries on the Islamabad Expressway project will also be fenced.
So far, work on 12 km has been completed. Fencing is also being put up in other areas to prevent encroachments.
Fences are also being erected on the hills of Margalla and work has started from Noorpur Shahan area.
Member Engineering also informed about the ongoing work on Margalla Road. The meeting was informed that the terminal point of D-12 section where the overpass would be constructed at the cemetery would be finalized within two weeks.
As no land is being acquired in GT Road to D-12 section, this section will be completed this year.