AGL40.21▲ 0.18 (0.00%)AIRLINK127.64▼ -0.06 (0.00%)BOP6.67▲ 0.06 (0.01%)CNERGY4.45▼ -0.15 (-0.03%)DCL8.73▼ -0.06 (-0.01%)DFML41.16▼ -0.42 (-0.01%)DGKC86.11▲ 0.32 (0.00%)FCCL32.56▲ 0.07 (0.00%)FFBL64.38▲ 0.35 (0.01%)FFL11.61▲ 1.06 (0.10%)HUBC112.46▲ 1.69 (0.02%)HUMNL14.81▼ -0.26 (-0.02%)KEL5.04▲ 0.16 (0.03%)KOSM7.36▼ -0.09 (-0.01%)MLCF40.33▼ -0.19 (0.00%)NBP61.08▲ 0.03 (0.00%)OGDC194.18▼ -0.69 (0.00%)PAEL26.91▼ -0.6 (-0.02%)PIBTL7.28▼ -0.53 (-0.07%)PPL152.68▲ 0.15 (0.00%)PRL26.22▼ -0.36 (-0.01%)PTC16.14▼ -0.12 (-0.01%)SEARL85.7▲ 1.56 (0.02%)TELE7.67▼ -0.29 (-0.04%)TOMCL36.47▼ -0.13 (0.00%)TPLP8.79▲ 0.13 (0.02%)TREET16.84▼ -0.82 (-0.05%)TRG62.74▲ 4.12 (0.07%)UNITY28.2▲ 1.34 (0.05%)WTL1.34▼ -0.04 (-0.03%)

CEO CBD Punjab directs swift completion of Walton railway crossing flyover

Ceo Cbd Punjab Directs Swift Completion Of Walton Railway Crossing Flyover
Share
Tweet
WhatsApp
Share on Linkedin
[tta_listen_btn]

Imran Amin CEO of Punjab Central Business District Development Authority (PCBDDA) chaired a significant review meeting, to assess the progress of ongoing development projects. The authority also known as Central Business District Punjab (CBD Punjab), is working on major infrastructure enhancement projects including CBD Route 47, Walton Railway Crossing Flyover, and Walton Road.

During the meeting, CEO CBD Punjab, Imran Amin, was briefed on the current status of all projects.

He directed that the water-bound layer at Walton Road Railway Crossing Flyover be completed swiftly, and asphalt work should begin promptly.

The meeting was attended by Executive Director Technical Riaz Hussain, Director Construction Asif Babar, Director Project Management Asif Iqbal, Director Architecture and Planning Sameer Aftab Sial, senior officials from NESPAK and NLC, and the project contractors.

CEO CBD Punjab,Imran Amin was informed that the asphalt work from Defense Mor to Qainchi on Walton Road has been completed and the road is now open for traffic.

Additionally, the final asphalt layer on Major Ishaq Shaheed Flyover is also complete and it will be fully operational for traffic within a day or two.