AGL37.93▼ -0.2 (-0.01%)AIRLINK136.44▼ -4.85 (-0.03%)BOP5.45▼ -0.17 (-0.03%)CNERGY3.81▼ -0.05 (-0.01%)DCL7.5▼ -0.05 (-0.01%)DFML46.21▼ -1.19 (-0.03%)DGKC80.08▲ 0.42 (0.01%)FCCL27.97▲ 0.45 (0.02%)FFBL55.47▲ 0.84 (0.02%)FFL8.55▼ -0.05 (-0.01%)HUBC112.73▼ -0.69 (-0.01%)HUMNL12.33▲ 1.12 (0.10%)KEL3.85▼ -0.13 (-0.03%)KOSM8.02▼ -0.51 (-0.06%)MLCF35.08▲ 0.03 (0.00%)NBP65.9▲ 2.28 (0.04%)OGDC170.46▲ 0.62 (0.00%)PAEL25.25▲ 0.07 (0.00%)PIBTL6.15▲ 0.27 (0.05%)PPL132.25▲ 5.98 (0.05%)PRL24.41▼ -0.4 (-0.02%)PTC14.52▲ 1.32 (0.10%)SEARL58.9▲ 1.59 (0.03%)TELE7.07▼ -0.09 (-0.01%)TOMCL34.95▲ 0.01 (0.00%)TPLP7.94▲ 0.45 (0.06%)TREET14.23▼ -0.1 (-0.01%)TRG45.68▼ -0.81 (-0.02%)UNITY25.67▼ -0.39 (-0.01%)WTL1.2▲ 0 (0.00%)

LESCO single-phase meter demand notice fee update for September 2024

Share
Tweet
WhatsApp
Share on Linkedin
[tta_listen_btn]

Lahore Electric Supply Company is a Pakistani government-owned electric distribution company, which provides connections to consumers to use electricity in its jurisdiction.

The LESCO jurisdiction comprises districts of Lahore, Okara, Sheikhupura, Nankana and Kasur in the Punjab province.

It is required to apply for a new connection if you want to avail the electricity services offered by the LESCO in the above mentioned districts.

There is an online process to submit the application for the new meter connection.

Lesco New Connection Procedure

Step 1: You can visit the given link (http://www.enc.com.pk/) to start the application process.

Step 2: Enter required information in the form such as NTC, connection type, area, CNIC Number, minimum load, premises address and others.

Step 3: You will also require to submit property details where you want to install the new electricity connection.

Step 4: After filling and uploading all required information and docs submit the application form

Step 5: Need to printout of your submitted application form

Step 6: Attach all above mentioned documents with this application

Step 7: Send or submit this complete file (including application form and required documents) to your related office

Step 8: LESCO demand notice will be issued after verification of the submitted documents and info

Step 9: Now next step is to pay the LESCO demand notice to mentioned bank

Step 10: After paying demand notice, copy should be submitted to the concerned office for further process

Step 11: In this final stage the concerned office will verify the demand notice payment and after verification they will installed the connection

Cost of single phase meter connection in Lesco?

The official website of Lesco says estimated new connection fee is Rs7240  but it as the same recommends to contact the concerned office for fee confiramtion.

In various sub-division of Lahore, the Lesco offices are charging Rs18,000 to Rs25,000 for new single phase meter connection. The rate may vary in other districts where Lesco offers services.

 

Related Posts