Chief Minister Punjab Mohsin Naqvi visited the Rawalpindi Ring Road project late at night. CM issued necessary directions to Commissioner Rawalpindi and FWO officials for an early completion of the project. CM inspected the site of Khasala Khurd Adiala Interchange and reviewed progress being made on the project.
CM Mohsin Naqvi ordered to speed up work on the Rawalpindi Ring Road project adding that the pace of work should be expedited by deploying additional workforce.
CM while directing NESPAK to provide drawing work relating to the project at the earliest stated that earthwork is slow and should be accelerated along with increasing the number of dumpers.
CM directed Commissioner Rawalpindi to visit the project regularly and submit a report in this regard. CM remarked that he would himself monitor the Rawalpindi Ring Road project.
CM also visited the Camp Office of FWO. Colonel Nadeem of FWO gave a briefing about the working of earthwork. CM was also apprised about other matters relating to the project.
CM was informed during the briefing that the Rawalpindi Ring Road project is 38.3 km long and will consist of 6 lanes. Provincial Minister Doctor Jamal Nasir, Commissioner, RPO, CPO, Deputy Commissioner and FWO Officials were also present on the occasion.