AGL37.9▲ 0.08 (0.00%)AIRLINK131.56▼ -1.67 (-0.01%)BOP5.61▼ -0.03 (-0.01%)CNERGY3.79▲ 0.02 (0.01%)DCL8.68▼ -0.18 (-0.02%)DFML40.95▲ 0.01 (0.00%)DGKC88.5▼ -1.19 (-0.01%)FCCL35.25▲ 0.19 (0.01%)FFBL66.2▼ -0.34 (-0.01%)FFL10.37▲ 0.24 (0.02%)HUBC109.2▲ 2.64 (0.02%)HUMNL14.24▲ 0.91 (0.07%)KEL4.87▲ 0.02 (0.00%)KOSM7.01▲ 0.21 (0.03%)MLCF42.01▲ 0.48 (0.01%)NBP59.71▲ 1.06 (0.02%)OGDC184.8▲ 4.16 (0.02%)PAEL25.58▼ -0.04 (0.00%)PIBTL5.86▲ 0.06 (0.01%)PPL147.7▼ -0.07 (0.00%)PRL23▼ -0.16 (-0.01%)PTC16.34▲ 1.14 (0.08%)SEARL68.2▼ -0.49 (-0.01%)TELE7.26▲ 0.03 (0.00%)TOMCL35.75▼ -0.19 (-0.01%)TPLP7.52▲ 0.16 (0.02%)TREET14.2▲ 0.05 (0.00%)TRG50.87▲ 0.12 (0.00%)UNITY26.55▲ 0.1 (0.00%)WTL1.21▲ 0 (0.00%)

NTDC fined Rs50m for failing to restore power in timely manner

Share
Tweet
WhatsApp
Share on Linkedin
[tta_listen_btn]

Total power system collapse in January 2021

The National Electric Power Regulatory Authority on Friday imposed a fine of Rs50 million on the National Transmission and Despatch Company for its “inability to restore power supply in a timely manner” in the wake of the “total power system collapse” that occurred in January 2021.

According to the regulator, it took approximately 20 hours to restore the system.

In a press release, Nepra said that it had taken serious notice of the incident and constituted an inquiry committee to investigate the matter in light of its laws, rules and regulations.

“The committee conducted the said inquiry and presented a detailed report to the authority on the basis of which the authority initiated legal proceedings against the NTDC,” the statement said.

It further stated that an explanation was issued to the company on April 1, 2021, followed by a show cause notice on August 25, 2021.

Moreover, an opportunity of hearing was also granted to the NTDC on January 12, 2022, but, the NTDC failed to provide any satisfactory response and was found guilty of violating the relevant provisions of the grid code. “Therefore, the authority has imposed a fine of Rs50 million on the NTDC,” the statement said.

The regulator also pointed out that it had initiated legal proceedings against the power plants concerned for their “lapses, deficiencies and failure” in relation to the incident. It said this was currently “under process and being dealt separately”.

In January 2021, a major power breakdown had plunged the entire country, including major urban centres such as Karachi, Islamabad, Lahore and Multan, into darkness for up to 22 hours a little before midnight.

 