AGL39.71▼ -0.42 (-0.01%)AIRLINK189.85▲ 0.42 (0.00%)BOP9.83▼ -0.51 (-0.05%)CNERGY7.01▼ -0.2 (-0.03%)DCL10.24▲ 0.03 (0.00%)DFML41.31▼ -0.49 (-0.01%)DGKC105.99▼ -2.64 (-0.02%)FCCL37.72▼ -0.87 (-0.02%)FFBL93.41▲ 3.5 (0.04%)FFL15▼ -0.02 (0.00%)HUBC122.3▼ -0.93 (-0.01%)HUMNL14.31▼ -0.14 (-0.01%)KEL6.32▼ -0.02 (0.00%)KOSM8.12▼ -0.28 (-0.03%)MLCF48.78▼ -0.69 (-0.01%)NBP72.31▼ -2.51 (-0.03%)OGDC222.95▲ 9.54 (0.04%)PAEL33.62▲ 0.63 (0.02%)PIBTL9.67▲ 0.6 (0.07%)PPL201.45▲ 1.52 (0.01%)PRL33.8▼ -0.75 (-0.02%)PTC26.59▼ -0.62 (-0.02%)SEARL116.87▼ -1.32 (-0.01%)TELE9.63▼ -0.25 (-0.03%)TOMCL36.61▲ 1.19 (0.03%)TPLP11.95▼ -0.62 (-0.05%)TREET24.49▲ 2.2 (0.10%)TRG61.36▲ 0.46 (0.01%)UNITY36.06▼ -0.63 (-0.02%)WTL1.79▲ 0 (0.00%)

CPEC and Changing Nature of Energy Projects in Pakistan | By Zulkafil Hassan Khan

Share
Tweet
WhatsApp
Share on Linkedin
[tta_listen_btn]

CPEC and Changing Nature of Energy Projects in Pakistan


China-Pakistan Economic Corridor (CPEC) has been instrumental in drastically decreasing the energy deficit in the country.

Its power projects have been simulating industrialization which has now further increased export volumes.

Its numerous wind, solar and hydro-power projects have been making a difference in the life of millions of people due to which witches of darkness and shadows have been encircled.

Thus these are development- oriented and clearly not responsible for any kind of circular debt trap in the country.

Most recently, Special Assistant to Prime Minister (SAPM) on CPEC Affairs, Khalid Mansoor, has reconfirmed that power generation projects are in line with the country’s growing needs and not over and above the national requirements, which is being propagated to be the major cause of circular debt trap and capacity payment issues.

He further clarified that globally 30-35 percent surplus power is a critical prerequisite to ensure sustainable and uninterrupted power supply.

Unfortunately, the federal government has again failed to make a decision on making payments to the tune of Rs230 billion to Chinese power plants operating under the CPEC project.

Under the 2015 energy framework agreement, Pakistan is contractually bound to make timely payments to the Chinese power plants that were set up under the CPEC framework. But hopefully, it will be settled amicably and CPEC Phase-II will be started very soon.

The SAPM was of the view that the power generation was increased by the previous government considering the country’s expanding industrialization needs. He upheld that all the projects were set up in line with the NEPRA policy.

He strongly rejected the allegations of corruption and kickbacks in the power projects and termed them all transparent and open. He said that since now the country has adequate surplus power, which should be diverted to the Special Economic Zones (SEZs).

We are persuading the Chinese in particular and other investors in general to utilize the huge incentives, including fiscal ones being offered in the SEZs so as to turn the country into a huge industrial hub, he added. He further dismissed the impression of any souring of relations between the two iron brothers – Pakistan and China.

On the other hand, Pakistan has amicably extended project completion deadlines of five Chinese power plants having a generation capacity of 3,600 megawatts.

In this connection, the commercial operations dates of 884MW Suki Kinari Hydropower Project, 720 MW Karot Hydropower Project, 330MW Tel project at Thar block-II, 330MW ThalNova Thar block-II and 1,320MW Thar block-I have now been extended.

 

The decision was communicated during the 4th Pak-China Relations Steering Committee meeting, chaired by Planning Minister Asad Umar.

The ongoing projects under CPEC and the issues being faced by their investors were discussed in detail in the meeting. The Power Division Secretary informed the meeting that the issue of commercial operation date (COD) extensions for five power projects had been resolved.

 

Unfortunately, the projects are falling far behind the dates of commissioning agreed between the government of Pakistan and Chinese investors due to many complex and complicated reasons, mainly COVID-related delays and strikes at some projects.

 

The Steering Committee shared that an initial 132 KV line is being built to provide electricity from the national grid to meet Gwadar’s electricity demand.

In addition, provision of solar panels to 3,000 households of Gwadar and other short-term measures are also being initiated to ensure additional supply of electricity to the city.

Thus energy requirements of Gwadar will soon be matched. In this context, the Committee was informed that work on some sections of another CPEC project Quetta-Zhob Road project had been halted due to a stay order from the Islamabad High Court.

 

However, many Chinese companies have once again complained that the process of work visas has not been smooth and workers had to apply for business visas, which resulted in imposition of penalties and banning of entry of Chinese citizens to Pakistan. They said that about 90,000 Chinese visa applications were pending for a decision which should be resolved on a priority basis.

 

To resolve this issue, the Planning Minister Asad Umar has now asked the Ministry of Interior to coordinate with Chinese companies operating in Pakistan. He suggested that the companies’ letters may be demanded as proof for work visas to resolve the problems.

 

Furthermore, the Ministry of Planning said that issues related to industrial cooperation were also discussed in the said meeting. The Industries Department of Government of Punjab briefed the Committee on the steps taken to resolve the investors’ pending issues. It was also shared that the process for the appointment of Faisalabad Industrial Estate Development and Management Company (FIEDMC) CEO would be completed as soon as possible. The board of the company has already been reconstituted.

 

The meeting was further informed that due to non-resolution of many issues, over $900 million Chinese investment in Special Economic Zones could not materialize fully. For instance, the Easy Prefabricated Private Limited Company has paid for electricity and gas connections but the services have not been provided yet.

 

Similarly, the La He Trading International Private Limited has manufactured electrical bicycles and tricycles but their products cannot be brought on the road due to absence of road policy. The company was also facing issues in securing loans from the banks due to lack of land entitlement.

 

The Snow White Lavation Private Limited applied for allotment of land in Allama Iqbal Industrial City over four months ago but did not get any response from the government of Punjab. Other Chinese companies were facing problems in getting electricity and gas connections in these zones for months.

 

For further streamlining, easy and smooth completion and functioning of ongoing CPEC projects, both countries, all main stakeholders and private companies should chalk out a comprehensive future road-map to mapping out all the pending issues hindering inflow of FDIs in the country.

 

More focus should be given to green technologies, especially in the SEZs in the country. Intensified hydro-power generation is the need of the hour which would be a game changer for cheap energy supplies in the days to come.