Staff Reporter Islamabad
Zonergy, one of the leading Solar Energy Solutions Company, under its Corporate Social Responsibility program has joined hands with the Government of Punjab, Energy Department to setup a 3 x 100 MW flagship Solar Power Plant located at Quaid-e-Azam Solar Park, Bahawalpur under CPEC framework.
The signing ceremony was held in the Minister for Energy Punjab which formalizes the project.
3×100 MW of this three-phase 9×100 MW project is already completed that won Luban award, the highest award in the construction works in China.
The total investment for the first phase was around 3.125 billion Yuan. Zonergy 9 ×100 MW solar power project spans over 4500 acres of land.
Zonergy executes the project by IPP model and the investment of Phase I was USD 460 million. This project is listed as CPEC “Early Harvest” project.