67 pc work on Orange Line Metro Train completed

Orange-Line-Metro-Train-650x340.jpg

Salim Ahmed

Over 67 percent of civil work on Lahore Orange Line Metro Train Project has so far been executed alongwith completion of a bridge on Lahore Ring Road near Quaid-e-Azam Interchange for elevated viaduct for the train, which had been constructed up to a length of eight kilometers along package-I of the project.
Chairman of steering committee for the project Khawaja Ahmad Haassan informed this during the weekly progress review meeting, here, Wednesday. The meeting was told progress on package-I from Dera Gujjaran, G.T.Road to Chouburji was 82 per cent, on package-II from Choburji to Ali Town was 50 per cent, on Depot near Dera Gujran was 73 per cent while on Stabling Yard near Ali Town it was 63.5 per cent.
The meeting was informed that all the 341 transom and 670 U-tub girders required for construction of elevated viaduct along package-I have been precast while 292 out of these transoms and 518 U-tub girders have been launched for constructing eight kilometers long elevated track.

Share this post

PinIt
    scroll to top